Skip to main content
Commercial Masonry Restoration in Boca Raton by Anthony Pennacchi & Sons
Boca Raton, Florida

Commercial Masonry Restoration in Boca Raton

Boca Raton's Ordinance 5589 placed 242 commercial buildings on a formal recertification schedule. When a structural engineer's report identifies masonry deficiencies, the building owner has a defined timeline to address them and close the finding with the city's Building Official. That is a compliance obligation, not a maintenance conversation. Anthony Pennacchi & Sons has been restoring commercial masonry across Palm Beach County since 1947. We work with building owners, property managers, HOA boards, and facility directors in Boca Raton, whether ahead of an inspection, in direct response to a deficiency report, or as planned asset preservation on properties approaching the 30-year threshold. assessment, fixed-price proposal.

75+
Years
3,000+
Projects
4th
Generation
24/7
Emergency

FL License CGC1538576 · Fully insured · No-pressure quote

By Anthony Pennacchi & Sons Team·Reviewed by Paul Pennacchi, Owner · 4th Generation·Last updated: April 2026

Quick Answer

  • Engineer-of-record-ready: contractor docs, material data sheets, methodology specs.
  • Phased scopes that keep tenants in place and parking decks operational.
  • on-site assessment plus fixed-price written proposal. Call (561) 475-0775.

The Boca Raton Difference

What You Get When You Call Pennacchi

Six reasons Boca Raton owners trust us with their masonry.

Featured
75+
Years · 4 Generations

Family-Built Since 1947

Four generations of commercial masonry, concrete, and waterproofing restoration. The Pennacchi name has carried the same standard since before most of South Florida commercial stock existed.

3,000+ Projects Completed

Commercial, residential, historic, and industrial restoration across Florida, New Jersey, New York, and Pennsylvania.

Recertification Documentation

Our licensing + reporting satisfies Palm Beach County and city-level recertification requirements (Miami-Dade 40-year, Boca Ordinance 5589, Boynton 22-025).

Certified Jahn Applicators

Material-compatible repair on Mizner-influenced, historic, and architecturally protected commercial structures.

Local Palm Beach Office

2875 South Ocean Blvd., Suite 200-18, Palm Beach. Close to every commercial corridor in Palm Beach County.

Engineer-Coordinated Scopes

We coordinate directly with the engineer of record so the repair plan, methodology, and completion docs align with what the city requires.

See for yourself

Why Restoration Over Replacement

Why This Makes Sense For Boca Raton Owners

Tap any reason to expand.

Restoration at the right stage of deterioration costs a fraction of structural failure and full replacement.

A spalling parking deck or cracked facade signals deferred maintenance before a tenant meeting begins. Restoration restores the building's professional character alongside its structural integrity.

Commercial valuations reflect maintenance history. Deferred concrete repair creates a documented liability that buyers and lenders price into any transaction.

Threshold buildings require recertification on strict schedules. Having the right licensed contractor in place before inspection reduces re-inspection cycles and delays.

On barrier island properties, unchecked chloride infiltration progresses from surface spalling to structural steel corrosion. Restoration stops that progression at whatever stage it is caught.

We provide the contractor's affidavit, material data sheets, and completion records the structural engineer of record needs to file with the building department.

Catch It Early

Six Signs Your Masonry Needs Attention

Boca Raton homeowners often see the first signs on surfaces closest to the water, like Intracoastal pool decks and Mizner-era driveways in Old Floresta.

Chunks of concrete breaking from columns, beams, parking deck soffits, or balcony undersides indicate advanced corrosion pressure already at work.

Random intersecting cracks across a deck or facade panel suggest widespread deterioration of the concrete matrix that needs engineered assessment.

Orange or brown streaks beneath elevated decks or balconies confirm that reinforcing steel is actively corroding and expanding.

A section of parking deck or plaza that rings hollow has separated from the substrate. Under vehicle loads, this fails suddenly.

Rebar visible on columns, beams, or foundation walls indicates advanced deterioration that threatens structural capacity.

Open joints at window perimeters and expansion joints allow water into the envelope, driving facade staining, interior damage, and accelerated deterioration.

Seeing any of these signs at your Boca Raton property?

on-site assessment. Fixed-price written proposal.

Call (561) 475-0775

What We Restore

Surfaces We Repair At Boca Raton Properties

Pool decks to foundation walls. Every primary commercial masonry surface.

Parking Decks And Garages

High demand

Elevated parking structures face salt-air chloride exposure, vehicle load cycling, and drainage saturation. We restore deck integrity, apply traffic coatings, and replace failed expansion joints.

Building Facades And Exterior Walls

Spalling concrete facades, stucco cracking, and EIFS failure on commercial office buildings. On Mizner-influenced or architecturally protected facades, Jahn mortar restoration.

Balconies, Catwalks, And Walkways

Recert-critical

Balcony soffit spalling, failed fascia concrete, and railing embedment corrosion on multi-story commercial and condo buildings.

Columns, Beams, And Structural Elements

Load-bearing column spall repair, beam soffit restoration, and structural crack injection on commercial building frames.

Plaza Decks And Podium Slabs

Waterproofed plaza decks over occupied space require both structural repair and restored membrane integrity.

Stairwells And Entry Features

Concrete stair treads, landings, and entry plaza surfaces where appearance and slip resistance both matter.

Technical Methods

How We Actually Do The Work

The details that separate a 30-year repair from one that fails next wet season. Click any method to see how it works in Boca Raton conditions.

Method 01 of 06

Spall Repair On Structural Elements

SpecPolymer-modified mortar

Commercial spall repair follows a more demanding sequence than residential because the affected elements often carry load and recertification inspections require documentation. Spalled sections are mapped, tested for delamination depth, and removed to clean, chloride-free concrete. Polymer-modified repair mortars are applied in correctly profiled lifts with full surface preparation and mechanical bonding profile.

Materials We Specify

Built For South Florida Exposure

A repair mortar that performs in a northern state may fail within a year in Boca Raton. We specify based on the conditions each surface actually faces.

M01

Polymer-Modified Repair Mortars

Structural spall repair

Bond strength, chloride resistance, and surface profile compatibility that commercial spall repairs require. Specified with the compressive strength, flexural bond, and chloride diffusion data engineering reports request.

M02

Epoxy & Polyurethane Injection Resins

Structural cracks

Epoxy for dormant structural cracks. Low-modulus polyurethane for active and water-transmitting cracks. Both specified with elongation and compressive data appropriate for the element type.

M03

Traffic-Grade Waterproof Coatings

Parking + plaza

High-build traffic coatings with aggregate broadcast. Waterproofing, UV resistance, and slip-rated surfaces for parking decks, plazas, and pedestrian walkways.

M04

Silane-Siloxane Penetrating Sealers

Below-surface chloride block

Prevent re-entry of chlorides into restored concrete elements. Specified at the appropriate silane content for the concrete porosity of the element being treated.

M05

Jahn Restoration Mortars

Period-compatible

Used on Mizner-influenced commercial facades, historic structures, and any building where the city's design standards require material compatibility with the original construction.

Our 6-Step Process

From First Call To Final Walkthrough

Every project follows the same disciplined sequence. No improvising, no shortcuts.

01
Day 1

On-Site Assessment

We inspect every affected element, perform delamination mapping, depth testing, and substrate evaluation. For recertification properties, we review the engineer's deficiency report alongside our findings.

02
Within 1 week

Written Scope And Fixed-Price Proposal

Written scope with a fixed price. For recertification scopes, includes material specs, mix designs, and methodology that the building department and the engineer of record require.

03
Pre-mobilization

Pre-Construction Coordination

Coordinate with property managers, HOA boards, building engineers, and tenants. Phasing plans, parking deck traffic management, and tenant communication established before site mobilization.

04
Day 1 of work

Surface Preparation

All deteriorated and chloride-contaminated concrete removed to the correct depth before any repair material is introduced. The step that determines whether the repair holds for the life of the building.

05
Main scope

Repair And Restoration

Repair mortars, injection resins, traffic coatings, waterproofing membranes, and sealers applied in correct sequence. We provide contractor's affidavit, material data sheets, and completion docs for recertification scopes.

06
Close-out

Final Inspection And Documentation

We walk every restored element with the property manager before close-out. On recertification scopes, we provide the written completion documentation the engineer of record needs to file with the city.

The Honest Answer

Restoration Vs Replacement

Some contractors push replacement because it generates a larger contract. We do not. Here is the head-to-head.

Recommended

Restoration

What we recommend in the majority of cases we assess in Boca Raton.

Typical cost
Fraction of replacement
Disruption to occupants
Phased; building stays operational
Time to complete
Weeks for most commercial scopes
Recertification posture
Strengthens compliance record
Best for
Spalling, cracking, joint failure, facade deterioration
Asset value impact
Preserves and improves valuation
Last resort

Replacement

When the substrate is gone or the structure is past saving.

Typical cost
Full structural rebuild
Disruption to occupants
Significant; partial or full vacancy
Time to complete
Months including engineering
Recertification posture
Resets full inspection cycle
Best for
Total structural failure or unsuitable substrate
Asset value impact
Major capex with long ROI horizon

We give you a straight answer after the assessment, not after looking at the size of the contract.

Why Choose Us

Six Reasons Boca Raton Owners Pick Pennacchi

The credentials, the people, the standard. Why Pennacchi, in six.

01
4 Generations · 1947

4th-Generation Commercial Experience

We have been restoring commercial concrete and masonry for longer than most of South Florida's commercial building stock has existed.

02
Engineer-ready

Recertification Documentation Capability

We understand the city recertification ordinances (Miami-Dade 40-year, Boca 5589, Boynton 22-025) and the repair plan submission requirements they create.

03
Palm Beach

Local Office, Not A Franchise

2875 South Ocean Blvd., Suite 200-18, Palm Beach. Every commercial corridor in Palm Beach County is within close reach.

04
Jahn Certified

Jahn Applicator Certification

Where commercial facades involve Mizner-era or architecturally protected construction, our Jahn certification is the credential that makes it achievable.

05
Honest

Transparent Assessments

We assess properties on what the structure actually shows. If restoration will hold and deliver lasting value, we document it. If it will not, we say so and explain why.

06
3,000+

Projects Across Four States

Residential, commercial, historic, and industrial restoration across Florida, New Jersey, New York, and Pennsylvania.

Our reputation is the only thing we will never restore if we damage it.

Frequently Asked

Boca Raton Masonry Restoration FAQ

The questions Boca Raton owners ask most. Tap any to expand.

When water infiltrates a failed mortar joint and the wetting and drying cycles that follow break down the mortar behind it, moisture reaches the masonry unit and, on reinforced structures, the steel embedded within. On a Boca Raton commercial building that has been accumulating Atlantic chloride exposure since the 1980s, that process is often already at an advanced stage by the time an Ordinance 5589 inspection reveals it. Commercial masonry restoration addresses those failures using materials matched to the original construction and specified for the structural and compliance requirements the building faces, not just for the visual surface.

4th-generation commercial masonry craftsmanship since 1947. The diagnostic depth and material knowledge built across 75+ years of commercial masonry work in South Florida are not available from a contractor that started recently. Reading structural deficiency reports, specifying Ordinance 5589-compliant remediation scopes, and delivering the documentation that closes city findings require experience that cannot be acquired quickly.

Share the engineering deficiency report with us and we will review it before the site assessment. We scope commercial masonry restoration work to directly address each deficiency line item, provide material data sheets, mix design references, and contractor methodology documentation for the structural engineer of record, and deliver the written contractor affidavits and completion documentation that Boca Raton's Building Official requires to close Ordinance 5589 findings. We do not ask the building owner to manage the gap between what the engineer has identified and what the contractor proposes. Those two things need to align, and we make sure they do from the first proposal.

Properties east of the Intracoastal in Zone 1 of Boca Raton's inspection priority schedule face sustained Atlantic chloride exposure that penetrates mortar joints and stucco systems continuously, not just during storm events. The chloride concentration on the barrier island and immediately west of the Intracoastal is significantly higher than on inland commercial properties of the same age and construction type. Ordinance 5589's decision to prioritize Zone 1 inspections reflects precisely that accelerated deterioration pattern. For east-side commercial buildings, this means masonry joint failure, stucco delamination, and structural spalling typically appear ten to fifteen years earlier than on comparable properties further inland.

Yes. Phasing restoration work around occupied commercial buildings, operational retail tenants, and active parking structures is standard practice for our team. We work with property managers and facility directors to sequence each phase so that access to critical building areas is maintained throughout the work. The phasing plan is included in the written proposal before any work begins, and it is developed in coordination with the building's management team rather than imposed after mobilization.

Yes on both counts. Commercial masonry repair work in Boca Raton requires a building permit, and Florida law requires that the work be performed by a licensed contractor. On Ordinance 5589 compliance scopes, the permit process is part of the documentation chain that leads to the city's Building Official accepting the remediation as closing the deficiency finding. Permit documentation requirements are set by the jurisdiction. We carry full licensure and insurance on every commercial project we take on in Boca Raton.

Ready to start?

Get Your Assessment In Boca Raton

If your property is showing signs of masonry deterioration, the right time to have it assessed is before the damage reaches the reinforcing steel. No-obligation on-site assessments throughout Boca Raton and Palm Beach County.

Anthony Pennacchi & Sons · 2875 South Ocean Blvd., Suite 200-18, Palm Beach, FL · FL License CGC1538576